Power supply is half of the demand in Pabna, there is no power in Dinajpur for 6-7 hours

Like many other parts of the country, the demand for electricity has increased in Pabna and Dinajpur due to the intense summer heat. Load-shedding has increased in both districts as supply falls short of demand. This disrupts production in industries, creates irrigation crisis in agriculture and increases the suffering of common people.

In Pabna, electricity supply has halved compared to demand. On the one hand, production is reduced due to loss of working hours in factories, on the other hand, agricultural crops are disrupted. However, the heads of electricity supply companies did not want to comment publicly on this matter.

Talking to at least 10 residents of the district town, it is said that loadshedding is happening 5 to 6 times in 24 hours every day. There is no power for about an hour each time. The city dwellers have to stay without electricity for 5 to 6 hours.

Yasin Ali runs a small industrial enterprise in the district town. He said that various food products including Chanachur and chips are made in his company. Workers work from 9 am to 5 pm; But during this period the power went out at least four times. In this, the workers sit and take salary, the production also decreases.

Northern Electricity Supply Company (NESCO) supplies electricity to the district town. When asked about this, Nesco Executive Engineer Mostafizur Rahman refused to give any information. He said, "I can't say anything about electricity at the moment. If you want to know about demand and supply, you have to contact the head office.

However, a Nesco official said on condition of anonymity that the daily electricity demand in the district town is 41 to 47 megawatts. 17 to 22 MW is being supplied there.

ABM Fazlur Rahman, director of Pabna Chamber of Commerce and Industry, said that production in every factory in the district has come down to half due to load shedding of electricity. Working hours of workers are being wasted. As the production decreased, the cost of the factory owners also increased.

The picture is the same at the upazila level. According to sources of Pabna Palli Vidyut Samity-2, the daily electricity demand in their area is 97 MW. There is a supply of 75 to 80 MW. As a result load shedding is happening in various areas.

Farmer Sujan Hossain of Vitbila village of Sujanagar upazila said that the power outage has reached its peak. Electricity goes out four to five times a day and night. It is disrupting irrigation. However, the crops have not been damaged due to the rain. However, if the electricity supply decreases during the absence of rain, the farmer will face losses.

Uttam Kumar Saha, DGM of Pabna Palli Vidyut Samiti-2, said that the supply of rural electricity is still good. 15 to 17 MW electricity is less than the demand. But there is no problem with it.

Load shedding has also increased in Dinajpur for more than a week. Residents said that especially in rural areas, there is no electricity for six to seven hours day and night.

Moslem Uddin (62), a resident of Biral Upazila's Mahajanpara area, said, "The power went out at 12 noon on Saturday, and it came back at 2:30. Then left at 8 pm, arrived on Sunday at 11:30 am. However, there may have been problems due to the storm yesterday; But now electricity problems have increased. There is no electricity for at least six to seven hours in 24 hours.

Talking to at least 15 residents of Dinajpur Sadar, Birol and Bochaganj upazilas, auto rice mill owners and farmers, similar complaints were found.

Molly Rani, a resident of Chhotagurgola area of ​​the city, said, 'The electricity goes off three to four times during the day. Father sick at home, small child. Cooking has to be done in an electric oven. All in all, I am suffering.

According to Dinajpur Palli Vidyut Samiti-1 sources, the demand for electricity in summer is 100 to 122 MW. But now the supply has dwindled. 25 to 30 MW less electricity is available against the demand at various times.

Seema Rani Kundu, Deputy Manager (Technical) of the association said that the supply has decreased slightly against the demand. For this, some feeders have to be closed for one to two hours depending on the area. Due to yesterday's heavy rain, there were connectivity issues in some areas. There is no problem of supply and demand for this.

Ahsan Habib, executive engineer of NESCO in Dinajpur said, "Power is being supplied through a total of 17 feeders. In peak summer our demand is 27-28 MW, normal time demand is 20-22 MW. Currently there is not much shortage. However, loadshedding has to be done for one hour in three-four feeders during the day.

Sahidur Rahman, director of Dinajpur Chamber of Commerce, said that there is no electricity for more than three to four hours a day. At present at least 40 percent are getting less electricity. Having to rely on diesel. It increases the cost of production.